Proposals for New Atomic Power Plants
New Delhi, Jan. 4 -- At present, there are nine (9) nuclear power reactors at various stages of construction, targeted for completion by 2024-25. In addition, twelve (12) more nuclear power reactors have been accorded administrative approval and financial sanction by the Government in June 2017. Thus, twenty one (21) nuclear power reactors, with an installed capacity of 15700 MW are under implementation, envisaged for progressive completion by the year 2031. The details are as follows:
State
Location
Project
Capacity
(MW)
Sanctioned Cost (Rs. crore)
Gujarat
Kakrapar
KAPP 3&4
2 x 700
11459*
Rajasthan
Rawatbhata
RAPP 7&8
2 X 700
12320
Tamil Nadu
Kudankulam
KKNPP 3&4
2 X 1000
39849
Kalpakkam
PFBR&
500&
5677
Haryana...